Method of Installation


 
STEP 1
Mix the appropriate proportion of CL-Bond G3 (1 bag - 20kg) and CL-FLEX 808 (1 can - 4 litre) into a suitably sized bucket. Stir thoroughly until a slump free mortar is obtained.
  STEP 2
A chalk line is to be done as a guide prior to installation. Masonry nails are nailed onto the substrates to prevent mouldings from sliding during the bonding process. Make sure the substrates are unpainted and free from dust.



 
STEP 3
Measure the correct lengths and cut to size. Apply adhesive mortar on the bonding surface of the moulding thoroughly with a notched trowel.
  STEP 4
Push and fix firmly onto the wall allowing the nails to puncture through the polystyrene. Ensure excess adhesive mortar is squeezed out from its sides.



STEP 5
Excess adhesive mortar should be removed with a steel scraper. Smears should be removed with a wet cloth or wet paint brush. Wash up tools immediately with water upon completion.



PAINTING WORK
1 coat sealer and 2 coats Arcylic emulsion paint are strongly recommend to SAO Moulding.